Queeny Tower interior demolition continues

Sent on behalf of Barnes-Jewish Hospital.

If you’ve driven Kingshighway recently, you may have noticed scaffolding and plywood being installed around Queeny Tower. It will contain the debris when structural demolition starts in February( see diagram.

In early February, a large crane will be installed inside the project site along Barnes-Jewish Plaza to remove rooftop equipment and to demolish connections to adjacent buildings. Structural demolition will will be completed by late September 2021.
More information on timing for the crane and start of structural demolition will be shared as the dates are finalized.

Contact Justin Breig, BJC planning, design & construction, at 314-323-2317 if you have questions or concerns.

 

Categories: Facilities Operations Update