Facilities Operations Update

Renard Loading Dock upgrades update

On Monday, August 23rd from 7am to 1pm, a boom truck will be installing the steel canopy above the Renard Dock. Please see the footprint of the boom truck and outriggers used to lift the steel into place. One of the compactor bays will be impacted by the placement of the truck. The installation of the canopy is estimated at roughly 4 hours.

Since there is only one door to enter Renard from the dock, someone will be onsite to direct and coordinate foot traffic with the work, and make sure that zero lifting/steel placement overhead will take place when staff or delivery person(s) needs to enter/exit the door into the Renard building to ensure pedestrian safety throughout this process. Please anticipate minor delays.

For any questions, please contact Engineering Project Manager, Antwoine Feaman.