CSRB North Tower Addition-Supply and Exhaust Air Systems Service Interruption 10/18/2021-10/21/2021

In support of the BJC MDAS (Multi-carrier Distributed Antenna System) project, the vendor will be installing the MDAS systems on the 4th floor of NTA during this outage on Monday, October 18th 9pm- Thursday, October 21st 6am. The supply and exhaust air systems serving the 4th and 5th floors will be off intermittently during this outage for maintenance purposes; however, minimal impact is expected to space temperature and humidity in the animal spaces. No work may occur in the 4th floor ABSL3 suites during this outage. The outage times will be as follows:

October 18th: 9:00 PM to 6:00 AM the following morning.
October 19th: 9:00 PM to 6:00 AM the following morning.
October 20th: 9:00 PM to 6:00 AM the following morning.