BJC Institute of Health Vertical Expansion site prep starts Monday, January 17, 2022 – reminder

On Monday, January 17, Alberici Construction will begin site preparations for the BJC Institute of Health (BJC IOH) Vertical Expansion Project. The project is a planned six (6) story vertical expansion addition on the existing north tower of the BJC IOH building. The addition will accommodate the expansion of specialty wet lab and wet lab research areas on campus.

Site preparation construction work (see attached sketch) from January 17, 2022 through March 28, 2022 will include:

• Mobilization – Starts January 17, 2022
• Closures
o Closure of Hope Plaza Area
o Re-Routing of Pedestrian Walkways Around the Plaza
o Closure of Wohl Circle – Wohl Circle will be closed to all traffic other than Chromalloy Dialysis Center

Patient Parking

• Site Preparation
o Start of selective building demolition on the BJCIOH building to prepare for steel erection
o Installation of crane and man hoist foundations
• Start of Steel Erection – March 28, 2022