Facilities Operations Update

MCC 8th Floor Exterior Window Replacement January 19th – January 24th

Beginning Wednesday, January 19th through Monday, January 24th work will commence to replace a damaged window on the 8th floor of MCC. The work will take place near the Southwest corner of the building next to the BJCIH service drive. The sequence of work will include:
• Mobilize and construct swing stage, January 19th
• Replace window on South side of building, January 20th
• Finalize installation, caulking and demobilize January 24th
Access to the BJCIH loading dock may be blocked for approx. 10 minutes on January 19th and January 24th while the swing stage is moved into place. This work is weather dependent and in the event of inclement weather, it will be rescheduled.

Please contact Project Manager, John Hardin, with any questions.