July 30 – September 23: East End of McKinley Avenue Closed for South Building Roof Replacement

Starting Wednesday, July 30, from 6 a.m. to 2:30 p.m., Monday to Friday, roofing contractors will block the east end of McKinley Avenue from the @718 Core Parking Lot to S. Euclid Avenue to set a crane for the South Building Roof Replacement Project. The crane will remain in place throughout the project’s duration.

The lift work will completely shut down the north sidewalk from the McDonnell Medical Science Building to S. Euclid Ave. The South Building entrance on McKinley will be closed. The entrance/exit to Core @ 718 will be open.

We expect the project to be complete by September 23.

If you have any questions, please contact Antwoine Feaman, Contracted Services/Engineering Project Manager, at afeaman@wustl.edu.