Taylor Avenue Building (TAB) parking lot drain repairs

The following upcoming work in the TAB parking lot will take place from June 21st – July 1st. We will begin the work by locating the utilities.

There will be no disruption to the area when this is performed. After this work is performed, it will be blocked off the point of entry to the parking lot for vehicles.

The parking lot will be left open to foot traffic around the work area. Once this is blocked off, the saw cutting of the pavement will be performed and excavation of the existing manhole and storm sewer will commence.
Once the area is excavated, the new storm inlet structure will be delivered and set into place.

Once this is complete, they will patch the asphalt and final clean up will be performed and the area will be re-opened for use.

Please contact Rick Myers, Senior Project Manager with any questions.