Sent on behalf of Barnes-Jewish Hospital. As renovations continue on the main level lobby at BJH South, work will begin on a busy corridor intersection. Contractors will partially block the area starting November 3 as they erect construction barriers. They plan to completely close the area on November 10 for approximately 5 months. Detour routes […]
Category: Facilities Operations Update
October 27 – November 17: Repaving of 4500 Forest Park Avenue
The east and westbound lanes of 4500 Forest Park Avenue will be repaved from October 27 through November 17. This work will occur in the evening to minimize traffic disruptions.If you have any questions, please contact Vern Watts, Director of Projects, vern.watts@wustl.edu.
October 27 – February 2026: Maternity Parking Lot Temporary Parking Spaces Closure
Starting on October 27, Tarlton will install construction fencing, a trash chute, and a dumpster in the alley between McMillan and Maternity for the demolition. The project will block five parking spaces in the Maternity Lot to allow access to the dumpster and will restrict access to the alley for safety reasons during the use […]
November 3 – April 2026: Plaza Entry Project to Close Corridor Intersection, Two Detour Options Beginning November 10
Sent on behalf of Barnes-Jewish Hospital. As renovations continue on the main level lobby at BJH South, work will begin on a busy corridor intersection. Contractors will partially block the area starting November 3 as they erect construction barriers. They plan to completely close the area on November 10 for approximately 5 months. Detour routes […]
October 27-November 17: Repaving of 4500 Forest Park Avenue
The east and westbound lanes of 4500 Forest Park Avenue will be repaved from October 27 through November 17. This work will occur in the evening to minimize traffic disruptions. If you have any questions, please contact Vern Watts, Director of Projects, vern.watts@wustl.edu.
October 27-February 2026: Maternity Parking Lot Temporary Parking Spaces Closure
Starting on October 27, Tarlton will install construction fencing, a trash chute, and a dumpster in the alley between McMillan and Maternity for the demolition. The project will block five parking spaces in the Maternity Lot to allow access to the dumpster and will restrict access to the alley for safety reasons during the use of […]
October 27 – November 10: St. Louis Children’s Hospital’s Second-Floor Outpatient Pharmacy and Admitting to Open Soon
Sent on behalf of Barnes-Jewish Hospital. After months of work and some necessary disruptions, construction is nearing completion on new spaces for the outpatient pharmacy and admitting in the former Eye Center space on the second floor. These moves are a precursor to renovations to the emergency department slated to begin late this year. More […]
October 20 – November 21: North Building Exterior Repairs with Accessible Ramp Closure the Week of October 27
Starting October 20, Fixture Contracting will make minor exterior repairs to the North Building on Euclid Avenue at Barnes-Jewish Plaza. The accessible exterior ramp will be closed to repair the concrete surface the week of October 27th. During this closure, the accessible ramp to Becker Library will remain open and provide alternate access to the […]
October 20-21: St. Louis Children’s Hospital’s New Donor Wall Installation is Closer to Completion; Overnight Corridor Closure
Sent on behalf of Barnes-Jewish Hospital. The prep work for the new donor wall installation on the second floor is nearing completion, and the construction barriers will come down later this week. The next step in the installation will require the closure of the second-floor corridor for about 10 hours starting at 6 p.m. on […]
October 20-31: Farrell Learning & Teaching Center (FLTC)/Eric P. Newman Education Center (EPNEC) Link Roof Tie-Off Installation
Fixture Contracting will use a lift to install the horizontal lifeline system on the walkway between EPNEC and FLTC. This work is scheduled for October 20 to October 31 and is weather-dependent. The work will be performed in 3 phases. Workers will start on the EPNEC side, with the lift set on the walk path […]