Sent on behalf of Barnes-Jewish Hospital. The first floor EU renovation of the 40s Pod area is nearing completion; however, with any construction, inconveniences are inevitable. The north/south corridor between the 40s and 50s Pods will briefly close at a short section on the following dates. The expedited work during the closure is expected to […]
Category: Facilities Operations Update
7/27-8/28: Ellen S. Clark Hope Plaza Restoration – Mid Campus Center (MCC) Front Entrance Disruption
Starting the week of July 27, 2026, and continuing through August 28, 2026, pending weather, the Phase 5B portion of the plaza at the MCC front entrance will be under construction. Work will be performed in and around the MCC front entrance and Metro Link platform. Please note and make arrangements to access MCC via […]
7/29-8/11: Avaya Technology Upgrades
Sent on behalf of BJC IT. BJC IT will be replacing the existing end-of-life Avaya G650 Voice Gateways at the locations listed below with new Avaya G450 Gateways. This upgrade will help ensure a stable voice environment for desk phones and reduce the risk of security vulnerabilities. The following analog devices will experience an outage […]
7/20-7/31: Manhole Audit Along Duncan Avenue and Euclid Avenue
Please be aware that beginning 07/20/26, Archkey Sachs will be working on the Medical Campus to conduct manhole audit activities along Duncan ave (4400 block) and Euclid Ave (200 block). (Please see the attached work location). Weather permitting, the planned duration of this work is from Monday, 07/20/26 through close of business, Friday 07/31/26. All […]
7/11-12: Temporary Closure of ADA Parking Spaces at 4444 Forest Park, Lift Access Required
Fixture Contracting is scheduled to repair a window on the east elevation of the sixth floor of the Forest Park Building on Saturday, July 11. A water test will be performed on Sunday, July 12. To complete this work, the contractor will use a lift that will require the temporary closure of two ADA parking […]
7/6-31: Biotechnology Building Corridor Water Cooler Replacement
Corridor Water Coolers in the Biotechnology Building are being replaced. The schedule is as follows: 1st Floor & Ground Level: Replaced beginning July 20, 2026, and will be completed by July 31, 2026. 2nd & 3rd floors: Replaced beginning July 6, 2026, and will be completed by July 17, 2026. If you have any questions, […]
August ’26: ServiceNow Field Service Management (FSM) Module is Coming to Enterprise Physical Operations
In August 2026, ServiceNow will be expanded to support Washington University’s Enterprise Physical Operations (EPO) Medicine and Danforth. WashU already leverages the ServiceNow platform for technology ticketing and asset management. WashU EPO will adopt the ServiceNow Field Service Management (FSM) module to centralize and streamline operations, enabling efficient management of maintenance requests, work orders, assets, […]
7/6-10: Demolition Work in McMillan Plaza to Begin
Beginning Monday, July 6, demolition work will begin in McMillan Plaza to accommodate the crane and construction laydown areas needed for the McMillan Phases 1–5 renovation. This work will include the selective removal of concrete and asphalt, as well as planting beds. Exterior demolition is scheduled to be completed by July 10. In addition, Phase 1 interior demolition of […]
6/27: Crane Operation at East Imaging Building
Weather permitting, on Saturday, June 27, from 6 a.m. to 8 a.m., Taylor Roofing will be operating a crane on the south side of the East Imaging Building as part of Project #230019 – East Imaging Roof Replacement. Below is a diagram showing the area closure required for crane operations and the location of an additional […]
June 22-July 10: Overnight Closures of Street-Level Entrance to Barnes-Jewish Hospital
Contractors will close the street-level entrance to Barnes-Jewish Hospital nightly, Monday through Friday, starting at 8 p.m. on Monday, June 22 and will reopen by 4 a.m. each morning. During this time, contractors will cut open sections of the escalators and use the resulting openings to provide ventilation and facilitate debris removal. The work is […]