In order to support construction on the vertical expansion of the Steven & Susan Lipstein BJC Institute of Health building, power to the above listed buildings will be transferred from dual feed temporarily to a single feed. This will allow work to take place on the medium voltage side. Throughout this work, there will be no interruptions to the buildings or its occupants. The switching schedule is as follows:
Sunday, March 13th: Between 11am and 1pm power feeds to these buildings will be switched to single feed
Sunday, March 20th: Between 11am and 1pm power feeds to these buildings will be switched back to dual feed