Mid Campus Center-Electric Service Interruption 3/7/2022-3/8/2022

In order to support construction on the vertical expansion of the Steven & Susan Lipstein BJC Institute of Health building, power to the Mid Campus Center building will be switched from a dual feed to a single feed for 24 hours. Throughout the entirety of this work, Facilities expects no interruptions or blips to users. The switching schedule is as follows:

Monday, March 7th: Between 6am and 8am electricians will switch from dual feed to a single feed
Tuesday, March 8th: Between 6am and 8am electricians will return the buildings power systems to a dual feed