Facilities Operations Update

WUSM Ambulatory Cancer Center (ACC) public realm work – Taylor asphalt

In conjunction with the public realm work, we are ready to perform the mill and overlay of Taylor Avenue from Duncan and Taylor to Forest Park and Taylor. We plan to do this on Thursday, November 2nd, 7 am – 9 pm and Friday, November 3rd, 7 am – 9 pm. Please see the plan for more information (weather permitting).

We will be maintain 2-way traffic through phases A and B and access to the UHSP and Alzheimer building’s lot. Flagmen will also help traffic navigate the construction during the schedule.

  • Thursday 11/2/23 – 7 am – 9 pm: Mill Phase A and Phase B
  • Friday 11/3/2023 – 7 am – 9 pm: Pave and stripe Phase A and Phase B

For any questions, please contact Paul Sedovic, Senior Project Manager, Capital Projects.