5/28: Planned Service Interruption – Fort Lab, Fire Alarm

On 5/28, from 5 am to 7 am, facilities will be conducting a fire alarm test to verify that updates are working properly. During the test audibles will be heard and strobes will be witnessed. there will be no need for evacuation. THIS IS ONLY A TEST.

5/22-5/26: Limited Service Interruption, Clayton Garage, Elevator

Elevator #60 in the Clayton Garage will be taken out of service to repair the cab floor. The elevator will remain out of service for the weekend to allow the glue for the new flooring to set up. All other elevators will remain in service during this time.

5/29-6/1: Planned Service Interruption – Clayton Garage, Elevator

From 5/29-6/1, Elevator #61 in the Clayton Garage will be taken out of service to repair the cab floor. The elevator will remain out of service for the weekend to allow the glue for the new flooring to set up. All other elevators will remain in service during this time.

May 26-June 12: Temporary Bridge Closure, 7th Floor Rand Johnson to 5th Floor Southwest Tower

Sent on behalf of Barnes-Jewish Hospital. For about three weeks, the bridge connecting Rand Johnson’s seventh floor to Southwest Tower’s fifth floor will be closed while four MRIs are removed from the Mallinckrodt Institute of Radiology building. Cranes will hoist equipment and MRIs over the bridge, so the closure is a necessary safety precaution. If […]

A Look Behind the Lobby Construction Walls

Sent on behalf of Barnes-Jewish Hospital. Goodbye, pink-and-green 1980s-era flooring and walls; hello, demolition zone. Since the BJH lobby construction barriers changed last month, the main floor lobby is unrecognizable behind the walls. By the end of October, all the lobby work will be finished, and the detours will end. In the meantime, the section […]

5/13-29: Conduit Placement on Clayton Avenue

Beginning May 13, Archkey began working on the Medical Campus to conduct conduit placement activities on the 4300 block of Clayton Avenue. Weather permitting, the planned duration of this work is from May 13 to May 29. All work will be done during the day shift, beginning daily at 8:00 a.m. and ending at 3 […]

5/15: Planned Service Interruption – 4560 Clayton, Electric

On 5/15, from 7 pm to 9 pm, , Facilities will be conducting an Emergency Generator and Automatic Transfer Switch (ATS) test for the newly installed mechanical equipment and general life and safety items in the facility. During this test, normal commercial power will be disrupted, and the facility will be on emergency power. A […]