April-August: Plaza Lobby Detour Changes

Sent on behalf of Barnes-Jewish Hospital. As renovations continue, areas reopen, and detours shift. Three new elevators to serve the main and street level lobbies opened in April. With the elevators, a new street-level lobby and atrium also opened, providing a street-level connection to the new Plaza West Tower. The corridor on the main level, […]

4/30-6/30: 4533 Clayton Avenue Building to Begin Construction

Construction will begin at the 4533 Clayton Avenue Building and run through the end of June 2026. The contractor will use the exterior stairway as the primary means of access, and a dumpster will be located on the west side of the building. There should be no disruptions to parking or daily operations. If you […]

5/2: Rehabilitation Institute Replacing 2 Roof Top Air Handlers

Sent on behalf of the Rehabilitation Institute of St. Louis. On May 2, the Rehabilitation Institute of St. Louis will be replacing two rooftop air handlers. The street and alley flanking the building will be closed to allow a crane and a semi-flatbed to operate. It is anticipated that this project will take one full […]

4/27-6/1: Ellen S. Clark Hope Plaza Restoration – Sidewalk Closures & Future Phases

Now that more favorable weather has arrived, we are planning to advance work in the plaza at a slightly faster pace, pending weather. Additionally, as we complete work in the center of the plaza, our upcoming phases will work in the perimeter areas of the plaza, such as the Mid Campus Center circle, closer to […]

4/23-24: Planned Service Interruption – Gary C. Werths Building at Siteman Cancer Center, Air Handling Unit

During the times noted below, Facilities technicians will perform preventive maintenance on the HVAC systems serving the 6th Floor Pharmacy Suite. During this maintenance window, no work may be performed inside the cleanroom spaces, and all cleanroom doors must remain closed. Facilities technicians will continuously monitor temperatures throughout the outage to ensure all affected spaces […]

5/7: Planned Service Interruption – Fort Labs, Fire Alarm System

On 5/7, from 5 am to 6 am, facilities, along with contractors, will be conducting a fire alarm A/V test of the reprogrammed fire alarm system. This is to ensure the system is operating as redesigned. Audibles will be heard, and strobes will be witnessed during the test on floors 2, 1, OA, and OB.

4/30: Planned Service Interruption – 1234 Kingshighway, Fire Alarm System

On 4/30, from 6 am to 6:30 am, facilities and the contractor will be conducting an A/V (Audio and Visual) test of the fire alarm system. There will be strobes witnessed and audibles heard throughout the building. THIS IS ONLY A TEST. There will be NO need to evacuate at this time.