Northwest Tower-Elevator Service Interruption 4/30/2023-5/3/2023

The elevators in Northwest tower are operating in emergency dispatch mode until further notice. This means that the elevators will operate continuously, stopping at random floors going up then back down. For example: Going up an elevator may stop at all the odd numbered floors, then coming down it will stop at even numbered floors. […]

Southwest Tower-Fume Hoods Service Interruption 5/6/2023

Facilities will be making repairs to fume hoods that are located on floors six, seven, and eight. No work should be done in the lab area fume hoods on Saturday, May 6th 6 am – 12 pm. The BTCF area will not be affected by this outage.

REVISED – McDonnell Pediatric Research Building, CSRB North Tower Addition, Clinical Sciences Research Building, Wohl Hospital, Wohl Clinic, Renard Hospital, Barnard Hospital-Electric Service Interruption 5/16-19/2023

Facilities Electricians will need to perform switching in the CSR-Substation, which provides power to the above listed buildings. This is to support Ameren de-energizing their equipment for maintenance work. May 16th 6 am – 19th 7 am , the CSRB Substation will be single lined to one utility, instead of the normal two utilities. We […]

Clayton Garage generator project starts Monday, May 8

On Monday, May 8th Clayton Garage generator project will begin with replacing the old generator. We will be blocking off 12 spaces during the project. The north alcove and 6 spaces west of the exhaust stake. This project is projected to carry on through September or early October. We will open up spaces as soon […]

McDonnell Pediatric Research Building-Air Handling Unit Service Interruption 5/8-20/2023

A contractor will be cleaning a portion (the large vertical riser) of the supply air ductwork served by the laboratory supply air unit, AHU-1. This unit serves laboratories on the northwest side of the building (roughly half of the laboratory facilities in MPRB). This will impact all of the BSL3 suites in MPRB. To minimize […]