Update on Kingshighway utility work – March 20-25

Sent on behalf of Barnes-Jewish Hospital. Contractors will continue the utility work in northbound Kingshighway, which was started last month, in five consecutive days versus six weekends as originally planned. This will reduce the ongoing disruption and provide a safer environment for the workers. The work will start at 8 pm, Wednesday, March 20 and […]

Maternity west side tuckpointing project restarts March 4th

The Maternity west side tuckpointing project will restart on Monday, March 4th. The work will be performed on nights between 6 pm – 8 am. The facade will be accessed by the swing stage. The work is isolated to the Maternity pit area and should have minimal impact on the surrounding area and campus operations.For […]

McDonnell Pediatric Research Building-Electric Service Interruption 3/8/2024

On Friday, March 8th 5-6 am Facilities Electricians will be working with contractors to install meters in the 5KV switchgear cabinet doors, this will be the 2nd of 2 outages. During the above date and time, feeds will be one-lined to the “D” feed to isolate the “W” 5KV switch for work to be done. […]

McDonnell Pediatric Research Building-Electric Service Interruption 3/7/2024

Facilities Electricians will be working with contractors to install meters in the 5KV switchgear cabinet doors, this will be the 1st of 2 outages. On Thursday, March 7th 4:30-6:30 am feeds will be one-lined to the “W” feed to isolate the “D” 5KV switch for work to be done. After work is completed switching will […]

REVISED-Farrell Learning & Teaching Center, North Medical Building, Cancer Research Building, South Medical Building, Bernard Becker Medical Library, Olin Residence Hall, McDonnell Medical Sciences Building, East McDonnell Facility, Couch Biomedical Research Building, 4522 McKinley, Specialized Research Facility East, Specialized Interim Research Building, Facilities Engineering Supply Room-Electric Service Interruption 3/31/2024 3-7 am

The purpose of this outage is to perform maintenance and testing on the ‘W’ feed portion of the McKinley Substation switchgear. Facilities electricians will perform switching in all affected buildings, to isolate and de-energize the ‘W’ feed. Facilities electricians and Service Contractors will inspect and test the breakers, relays, and major components of the de-energized […]

CSRB North Tower Addition-432/442 ABSL3 Suite Service Interruption 3/11/2024

On Monday, March 11th 6 am-10 pm Johnson Controls will be replacing the network control engine that serves 432/442 ABSL3 suite. NO work may occur in the 432/442 ABSL3 suite during this outage. All other ABSL3 suites in the 4th floor biohazard area will be available during this outage.