Sent on behalf of the University of Health Sciences and Pharmacy. The total roof replacement for the south residence hall project will be approximately two months (weather dependent). The impact will be on the core of the UHSP campus near Chick-fil-A. Please see the map. For any questions, please contact Eric Knoll, Vice President for […]
Author: Melanie
Couch Biomedical Research Building-Air Handling Unit Service Interruption 10/23-10/24/2023
On Monday, the 23rd, from 5 pm to 12 am on the 24th, Air handler number 2 will be off for motor replacement in the Couch Biomedical Research Building. During this time, all floors will have 50% heating/cooling and airflow to the west side of the building.
East Imaging Center-Air Handling Service Interruption 10/20/2023
On Friday, October 20th from 5 am to 10 am, work will be performed on Air handling unit 1B in the East Imaging Center. At this time there will be low airflow to the first floor.
McDonnell Pediatric Research Building-Exhaust Fan Service Interruption 11/4-11/13/2023
In order for facilities technicians to replace exhaust fan motors serving BSL3 suite 7230 outages are needed on the schedule noted below. During these times NO work shall take place in the BSL3 suite 7230. 11/4 5 am – 7 am11/6 5 am – 7 am11/11 5 am- 7 am11/13 5 am-7 am
North Medical Building-Noise 10/30-11/3/2023
On Monday, October 30th from 7 am to Friday, November 3rd at 4 pm in the North Medical building there may be noise and vibration for installing fall protection. During this week there will be heavy drilling on the roof which may be heard through the building.
Rescheduled – Barnes-Jewish Hospital Media Services drone shots October 17th and 20th
Sent on behalf of Barnes-Jewish Hospital. On October 17th and 20th, BJH Media Services will fly a drone around campus. Media Services will shoot low-altitude time-lapse shots, flying around 60 feet to show the busy campus ground traffic. This will occur near the green space at Scott and Taylor Avenues across from the Taylor Avenue […]
Barnes-Jewish Hospital’s New Patient Care Tower
Sent on behalf of Barnes-Jewish Hospital. Contractors are nearly two years into constructing the new patient care tower at Barnes-Jewish Hospital, which will transform the skyline along Kingshighway – and patients’ lives – now and well into the future. Get a behind-the-scenes look inside the new tower, see some time-lapse footage, and hear the perspectives […]
Closure of 4 spots on 4515 parking lot
The 3rd floor of the East McDonnell (EMD) Building will undergo a full gut renovation to create the new WU-GREaT gnotobiotic research facility, beginning in October 2023 and completing mid-2024. During that time, the General Contractor will utilize a portion of the 4515 parking area on the east side of EMD for site logistics, staging, […]
Forest Park Avenue shutdown from Euclid to Taylor for Ambulatory Cancer Center tower crane removal October 26-October 29th
Removal of the tower cranes for the new Ambulatory Cancer Center is planned for October 26th-29th. The activities will impact all eastbound vehicular and pedestrian traffic on Forest Park Avenue from Euclid to Taylor. Through traffic signs, vehicular traffic will be rerouted to turn North at Euclid towards Laclede Avenue or South towards Parkview Place. […]
Biotechnology Center-Cold Room 118 Service Interruption 10/13-11/30/2023
On Friday, October 13th from 7 am to November 30th at 3:30 pm cold room 118 in the Biotechnology Center building will be taking offline for service. During this time there can be nothing stored in this cold room.