BJC Institute of Health – Hope Plaza restoration – construction update

The project construction manager BSI Constructors, Inc., began mobilization on site the week of December 23th. While hampered by weather, work in the plaza began the week of January 6th. Initial construction will involve excavating the rock from the planter beds and removing the sidewalk areas within the existing job site fence. Work will also […]

Clinical Sciences Research Building North Tower Addition (CSRB-NTA) ninth-floor link

Workers will start upgrading the elevator lobbies in the CSRB-NTA on Monday, January 20th through May 16th, 2025. The scope includes the area from the door to the CSRB to the expansion joints at the McDonnell Pediatric Research Building. Traffic will be rerouted during the construction for each floor and will take approximately 2 weeks […]

Plaza Garage entrance closure for five weekends

Sent on behalf of Barnes-Jewish Hospital. The remaining structure of the Plaza Garage lobby, the elevators, and the escalators will be demolished for five weekends beginning at 6 pm on Friday, January 17. Barnes-Jewish Plaza will remain open in both directions. While the street will remain open, contractors will close the patient and visitor entrance/exit […]

Shell Cafe Floor Recovery Project starts January 18th

Workers will refinish the hardwood floors in Shell Cafe from January 18-19. The area surrounding Shell Cafe will be closed during this time. If you have any questions, please contact Charmaine Parker-Lewis, Assistant Director, Environmental Services.

Four-month Kingshighway lane closure starts January 20th

Sent on behalf of Barnes-Jewish Hospital. The Campus Renewal Project is shutting down a northbound lane of Kingshighway just north of Barnes-Jewish Plaza for four months. Starting January 20th, workers will reduce Kingshighway to two northbound lanes. The closure is north of Barnes-Jewish Plaza, adjacent to the New Plaza West Tower. Team members and physicians […]

Wohl Hospital lower level final floor replacement January 20-21

Workers will install the final floor replacement in the lower level of Wohl Hospital (the small corridor to the south of Clopton Auditorium and the new sliding doors) January 20-21 from 6 pm until 4 am daily. Please see the map showing the floor to be replaced in purple and the alternate routes in yellow […]

MetroLink secure platform plan update-

Sent on behalf of Metro. Below are updates regarding the MetroLink Secure Platform Plan. The contractor will wire the turnstiles and gates at the Central West End (CWE) Station during the week of January 27th. Work on the remaining fencing on the southern side of the alignment is scheduled to begin in February. We have […]

Specialized Research Facility (SIRF) repairs

On Monday, December 30th, repair work will begin at the Specialized Research Facility (SIRF). The area in front of the building facing McKinley Avenue will be closed from December 30th to January 13th. We apologize for any inconvenience. If you have any questions, please contact Jaswinder Singh, Engineering Project Manager.