On Friday, April 21st 7-8 am a contractor will be replacing the WIFI router in the B120B ABSL3 Corridor. NO work may take place in the B120 BSL3/ABSL3 suite during this outage.
Category: Outages
Steven & Susan Lipstein BJC Institute of Health-Exhaust Fans Service Interruption 5/2-4/2023
As part of the BJCIH Lab Exhaust Systems Updates Contractors will be performing work on the roof mounted exhaust air handling unit on May 2nd 6 pm – May 4th 12 am. This will affect Lab exhaust fans and air handling units feeding floors 7 thru 11. There will be no available exhaust to the […]
East Imaging Center-Chilled Water Service Interruption 4/22-23/2023
On April 22nd and 23rd from 5 am to 5 pm both days, there will be an outage for the chilled water for Air handling units B-1 and B-2 in the East imaging building. At this time there will be limited cooling to the basement.
Steven & Susan Lipstein BJC Institute of Health-ABSL# Suite B120 Services Interruption 4/18/2023
In order to replace bulbs ABSL3 suite B120 will be out of service on April 18th 6-7 am. During this time NO work shall take place inside the suite.
McMillan Hospital-Air Handling Unit Service Interruption 4/15/2023
On April 15th from 6am to 6pm Air handling unit 11 will be down for repairs in McMillan Hospital. In these scheduled times there will be limited to no air flow and heating/cooling to floors 1, 3, 4, and 5 of McMillan.
McDonnell Pediatric Research Building BSL3 Lab 7302 Entry Door Service Interruption 4/14/2023
On Friday, April 14th 12 – 3 pm the entry door to BSL3 lab 7302 the lab will be put out of service for repairs . During that time NO work shall be allowed in the lab.
McDonnell Pediatric Research Building-Exhaust Fans Service Interruption 4/10-11/2023
Between April 10th 9 pm – April 11th 7 am testing will be completed on one of the 8201 BSL3 suite exhaust fans. Little to no impact is expected to 8201 suite pressures, air flows, and temperatures. No work may occur in the 8201 BSL3 suite during this outage.
Clinical Sciences Research Building-Southwest Entrance Vestibule Service Interruption 4/18/2023
On Tuesday, April 18th 4 pm – 8 pm the southwest entrance vestibule to the Clinical Science Research Building will be closed. Alternate access can be gained through the McDonnell Pediatric Research Building. This closure is needed in order to make necessary repairs to the heating system for this vestibule.
Couch Biomedical Research Building-Electric Service Interruption 5/7/2023
This will be the first of two outages. On Sunday, May 7th 7 – 11 am. The purpose of this outage is to perform maintenance and testing on the main electrical switchgear that distributes power throughout the 4515 Couch Building. This requires de-energizing half of the main electrical switchgear, fed from the ‘D’ utility, so […]
Mallinckrodt Institute Radiology-Air Handling Unit Service Interruption 4/16-4/17/2023
Contractors will be working on the air handler that feeds floors 1 through 7 in preparation for cleaning the entire air handler. This air handler will be off at various times throughout April 16th 8 am -17th 6 am. Floors 1 through 7 may experience loss of airflow and slightly warmer than normal temperatures during […]