9/24: MCC Network Taken Offline for Scheduled Maintenance

From 10 pm to midnight on 9/24, the MCC will be taken offline for scheduled network modernization. The outage will impact nearly all devices and systems connected to the Emergency Communications Center network. To ensure the safety and security of all persons, the following steps will be taken:

10/5-1/25: East End of McKinley Ave Closed, Scott Ave Closed for Roof Replacement

Beginning Monday, 10/5/26, through Friday, 12/11/26, Taylor Roofing will close the east end of McKinley Ave as part of Project #251006 – McDonnell Sciences Roof Replacement. Once the south side of the McDonnell Medical Sciences Building roof is complete, Taylor Roofing will mobilize to Scott Ave to complete the north side of the roof. The […]

10/2-10/11: Barnes-Jewish Plaza to Close Two Weekends in October

Two weekend shutdowns of Barnes-Jewish Plaza are planned for the milling and repaving of the road. The entire stretch of the road from Kingshighway Blvd. to Euclid Ave. will close during this work. Impacts include the following:  Much of the work over the past several years has resulted in an uneven surface with as much […]

9/21: Ellen S. Clark Hope Plaza Restoration – Pedestrian Sidewalk Changes

Starting Monday, September 21, construction will begin on the Phase 4, 5B and 6 portions of the plaza. Work will be performed in and around the Metrolink platform, the Eric P. Newman Education Center (EPNEC) west front entrance, and the sidewalk areas near Parkview Avenue. Please note and plan to access the plaza via the […]

9/21-25: Archkey Performing Manhole Activities on Duncan Ave

Starting Monday, September 21, Archkey will work on the Medical Campus to conduct manhole activities on the 4300 block of Duncan Ave and the 4500 block of McKinley Avenue. Weather permitting, this work is planned from Monday, September 21 through close of business on Friday, September 25. All work will occur during the day shift, […]

10/10: Planned Service Interruption – Clinical Science Research Building, Electric

On 10/10 from 7 am to 11 am, facilities personnel and contractors will be conducting maintenance inspections and repairs, as necessary, during the 1st of three planned scheduled outages of the building’s electrical systems. This scheduled outage will affect lighting, building mechanical power, air handling units (AHU), exhaust fans, water pumps, and other circulating pumps. […]

9/15: Limited Service Interruption – West Building, Vaccum

On 9/15 from 4 am to 6 am, Facilities will be shutting down the building vacuum system to allow for repairs to the water service supporting the system. During this shutdown, **no vacuum service will be available to laboratories or equipment that utilizes the building vacuum system**.

9/14-9/18: Limited Service Interruption – Mid Campus Center, Elevator

Elevators in MCC will be out of service, one at a time, each day between 7 am and 3:30 pm, to complete the 5-year fire recall testing as required by the Elevator Safety Unit of the Missouri Department of Public Safety. We will select the elevators based on customer needs and technical requirements.