From 10 pm to midnight on 9/24, the MCC will be taken offline for scheduled network modernization. The outage will impact nearly all devices and systems connected to the Emergency Communications Center network. To ensure the safety and security of all persons, the following steps will be taken:
10/5-1/25: East End of McKinley Ave Closed, Scott Ave Closed for Roof Replacement
Beginning Monday, 10/5/26, through Friday, 12/11/26, Taylor Roofing will close the east end of McKinley Ave as part of Project #251006 – McDonnell Sciences Roof Replacement. Once the south side of the McDonnell Medical Sciences Building roof is complete, Taylor Roofing will mobilize to Scott Ave to complete the north side of the roof. The […]
10/2-10/11: Barnes-Jewish Plaza to Close Two Weekends in October
Two weekend shutdowns of Barnes-Jewish Plaza are planned for the milling and repaving of the road. The entire stretch of the road from Kingshighway Blvd. to Euclid Ave. will close during this work. Impacts include the following: Much of the work over the past several years has resulted in an uneven surface with as much […]
9/21: Ellen S. Clark Hope Plaza Restoration – Pedestrian Sidewalk Changes
Starting Monday, September 21, construction will begin on the Phase 4, 5B and 6 portions of the plaza. Work will be performed in and around the Metrolink platform, the Eric P. Newman Education Center (EPNEC) west front entrance, and the sidewalk areas near Parkview Avenue. Please note and plan to access the plaza via the […]
9/21-25: Archkey Performing Manhole Activities on Duncan Ave
Starting Monday, September 21, Archkey will work on the Medical Campus to conduct manhole activities on the 4300 block of Duncan Ave and the 4500 block of McKinley Avenue. Weather permitting, this work is planned from Monday, September 21 through close of business on Friday, September 25. All work will occur during the day shift, […]
9/16: Utility Work near Clayton Avenue Building to Affect Sidewalk and Westbound Lane
Sent on behalf of Barnes-Jewish Hospital. To prepare for demolition of the Clayton Avenue Building at Clayton and Boyle Avenues, utility excavation will close sidewalks adjacent to the building and a westbound lane of Clayton Avenue. One westbound lane of Clayton Avenue will be closed daily, September 16-30, from 6 a.m. to 4 p.m. This […]
10/10: Planned Service Interruption – Clinical Science Research Building, Electric
On 10/10 from 7 am to 11 am, facilities personnel and contractors will be conducting maintenance inspections and repairs, as necessary, during the 1st of three planned scheduled outages of the building’s electrical systems. This scheduled outage will affect lighting, building mechanical power, air handling units (AHU), exhaust fans, water pumps, and other circulating pumps. […]
9/15: Limited Service Interruption – West Building, Vaccum
On 9/15 from 4 am to 6 am, Facilities will be shutting down the building vacuum system to allow for repairs to the water service supporting the system. During this shutdown, **no vacuum service will be available to laboratories or equipment that utilizes the building vacuum system**.
9/14-9/18: Limited Service Interruption – Mid Campus Center, Elevator
Elevators in MCC will be out of service, one at a time, each day between 7 am and 3:30 pm, to complete the 5-year fire recall testing as required by the Elevator Safety Unit of the Missouri Department of Public Safety. We will select the elevators based on customer needs and technical requirements.
9/15-9/16: Limited Service Interruption – McDonnell Medical Science Building, Air Handling Unit
From 5 pm on 9/15 to 12 am on 9/16, Air Handling Unit 2 will be shut down to support a contractor’s duct-cleaning work in the 469 suite. This shutdown will affect the North side of the 4th and 5th floors, including the BSL 3 Laboratory, room 562. During this time, the affected areas will […]