Outages

11/14: Planned Service Interruption – North Building, Electric

On 11/14 from 6 am to 10 am, contractor personnel will be replacing damaged conduits that house power cables supplying the North Building.

Due to the condition of the existing conduit, both NORMAL and EMERGENCY POWER will be de-energized one at a time. Emergency power will be de-energized 1st to allow the installation of temporary power and then restored followed by the Normal power.

A second power outage will be scheduled following the completion of the conduit repair to facilitate the restoration of the permanent power connections.

Please plan accordingly for the interruption to both NORMAL/ EMERGENCY power.