Contractors will close the street-level entrance to Barnes-Jewish Hospital nightly, Monday through Friday, starting at 8 p.m. on Monday, June 22 and will reopen by 4 a.m. each morning. During this time, contractors will cut open sections of the escalators and use the resulting openings to provide ventilation and facilitate debris removal. The work is […]
Author: Michelle
Main Level Corridor, North/South Link to Reopen by End of June in Barnes-Jewish Hospital
Sent on behalf of Barnes-Jewish Hospital. The Link Detour will officially conclude by the end of this month, when the section currently closed near the Mallinckrodt elevator lobby reopens. Note that the main-level elevator lobby work will continue through August, and the detour to Surgery Registration will remain from the McMillan corridor. The Plaza Entry […]
4/13-5/7: Overnight Power-Washing in Metro, Siteman, Newstead, and Clayton Garages
From April 13 to May 7, workers will power-wash the garages according to the schedule below. The work will be done after hours and will not affect parking. If you have any questions, please contact Price Carpenter, Manager, Transportation and Parking, at carpenter.j@wustl.edu.
3/23-Oct ’26: WashU Medicine Campus GIS Survey Begins
Starting March 23, Facilities Engineering (FE) will begin collecting data for a GIS Map. This will help FE create an accurate map, inventory, and data collection to improve efficiency, safety, and planning. The project will run through October of 2026. If you have any questions, please contact Antwoine Feaman, Project/Program Manager, at afeaman@wustl.edu.
3/23-3/26: S. Euclid Avenue Temporary Lane Closure
From March 23-26, from 6 a.m. to 5 p.m., one lane of S. Euclid Ave. will be closed for subsurface exploration activities. One lane of traffic will remain open at all times to allow access to Renard Dock. If you have any questions, please contact Bob Korte, Campus Architect, Senior Project Manager, at rkorte@wustl.edu.
3/26-4-17: Medical Campus Street Work on Clayton Avenue
Sent on behalf of Barnes-Jewish Hospital. Beginning March 26, Archkey will be working on the Medical Campus to conduct directional boring activities on the 4300 block of Clayton Avenue. Weather permitting, the planned duration of this work is from Thursday, March 26, through the close of business on Friday, April 17. All work will be […]
Reminder: How to Place Work Orders in ServiceNow for Facilities Services
As a reminder, the Facilities Integrated Service Center (FISC) is the central point of contact and processing for facilities work orders at WashU Medicine. The center serves as a liaison between campus customers, service providers, emergency responders, and business managers. They offer a variety of business services, including new employee badges, parking, and Metro cards (U-Passes). More […]
2/2-5: Clinical Sciences Research Building – North Tower Addition Restrooms, Sinks, Faucets Closed 10 p.m. to 6 a.m.
From February 2-5, 10 p.m. to 6 a.m., workers will replace multiple sections of the cracked sanitary line located in the lower-level mechanical room of the Clinical Sciences Research Building – North Tower Addition. This line is the main drain for the building; therefore, to prevent water/waste from draining into the open pipe, restrooms, faucets, […]
2/7-8: Euclid Avenue Closure
Weather permitting, on February 7-8, from 8 a.m. to 4 p.m., Euclid Avenue will be closed to complete geotechnical analysis of the subsurface conditions. A drill rig will be set up in the street to collect subsurface samples, and the street will be patched upon completion of the work. If you have any questions, please […]
1/17-18: Cooling Tower Work, Planned Steam Shutdown & Crane Activity for East McDonnell
As part of the East McDonnell Cooling Tower Replacement Project, from January 17-18, workers will shut down the 75-psi steam system serving the East McDonnell Building and place the final crane lifts required to set new cooling tower equipment on the roof. This activity represents a major milestone for the project, and the work has […]