August 18-29: Medical Campus Street Work Notification on Newstead Avenue

Sent on behalf of Barnes-Jewish Hospital. Starting August 18, Kaemmerlen Electric will be working on the Medical Campus to conduct duct bank construction activities on the 600 Block of Newstead Avenue. Weather permitting, the planned duration of this work is from August 18 through close of business on August 29.All work will be conducted during […]

August 18 – September 19: Pedestrian Bridge to the Plaza Lobby ADA Ramp to Close Temporarily; Temporary ADA Ramp to be Installed

Sent on behalf of Barnes-Jewish Hospital. Work to remove the temporary walls and complete the area along the ADA ramp leading from the pedestrian bridge to the Plaza lobby will begin on August 18. The ramp is expected to reopen by mid-September. Before closing the ramp, contractors will install a temporary ADA-compliant ramp for use […]

August 13-15: Medical Campus Street Work Notification on Newstead and Clayon Avenues

Sent on behalf of Barnes-Jewish Hospital. Starting August 13, Kaemmerlen Electric began working on the Medical Campus to pull fiber cable. Weather permitting, the planned duration of this work is from August 13 through the close of business on August 15. All work will be conducted during the day shift, commencing daily at 7 a.m. […]

September 28: Cafeteria in Plaza West Tower Opens and Old Cafeteria will Permanently Shutter

Sent on behalf of Barnes-Jewish Hospital. The first thing you’ll notice walking into the Plaza West Tower when it opens the week of September 28 is the cornerstone. Crafted of polished quartz surrounded by limestone, it pays homage to the beginnings of Barnes Hospital and The Jewish Hospital of St. Louis. It brings warmth to […]

August 4-15: Medical Campus Street Work Notification on Newstead Avenue

Sent on behalf of Barnes-Jewish Hospital. Starting August 4, Kaemmerlen Electric will be working on the Medical Campus to conduct duct bank construction activities on the 600 block of Newstead Avenue. Weather permitting, the planned duration of this work is from Monday, August 4, through close of business on Friday, August 15. All work will […]

Cancelled: 4560 Clayton Avenue Building Roof Repairs

Due to the extreme heat, we cancelled the crane pick for this project. We will reschedule it and communicate the new date.If you have any questions, please contact Antwoine Feaman, Contracted Services/Engineering Project Manager, at afeaman@wustl.edu.

May 20 – August 31: Barnard Controls Retrofit

Bernhard Engineering/ENFRA has begun investigating the entire Barnard exhaust fan #3 system throughout the building. This consists of an ENFRA/Bernhard Engineer walking around the whole building and following the ductwork through the ceilings to create an as-built of the system. They will remove ceiling tiles and look above the ceilings as needed throughout the building. We […]