On June 6, from 6 a.m. to 9 a.m., Taylor Roofing will be operating a crane on the south side of the East Imaging Building as part of Project #230019 – East Imaging Roof Replacement. Below is a diagram showing the area closure required for crane operations, and the location of an additional truck and […]
Category: Facilities Operations Update
5/29: Changes along Barnes-Jewish Plaza
Sent on behalf of Barnes-Jewish Hospital. The Plaza Entry portion of Campus Renewal continues along Barnes-Jewish Plaza, with the driveway and sidewalks spanning the front of the hospital nearing completion this summer. Changes in store starting May 29 include the following: Employees driving in this area need to be cautious and alert to changes and […]
May 26-June 12: Temporary Bridge Closure, 7th Floor Rand Johnson to 5th Floor Southwest Tower
Sent on behalf of Barnes-Jewish Hospital. For about three weeks, the bridge connecting Rand Johnson’s seventh floor to Southwest Tower’s fifth floor will be closed while four MRIs are removed from the Mallinckrodt Institute of Radiology building. Cranes will hoist equipment and MRIs over the bridge, so the closure is a necessary safety precaution. If […]
A Look Behind the Lobby Construction Walls
Sent on behalf of Barnes-Jewish Hospital. Goodbye, pink-and-green 1980s-era flooring and walls; hello, demolition zone. Since the BJH lobby construction barriers changed last month, the main floor lobby is unrecognizable behind the walls. By the end of October, all the lobby work will be finished, and the detours will end. In the meantime, the section […]
5/13-29: Conduit Placement on Clayton Avenue
Beginning May 13, Archkey began working on the Medical Campus to conduct conduit placement activities on the 4300 block of Clayton Avenue. Weather permitting, the planned duration of this work is from May 13 to May 29. All work will be done during the day shift, beginning daily at 8:00 a.m. and ending at 3 […]
5/30: Temporary Metro Garage and Nash Way Closure
The temporary closure of Metro Garage for the rooftop split replacement project will be on May 30, from 11 a.m. to 5 p.m. During this time, Nash Way will be closed just past the transfer center bus entrance while the crane is in operation. During the closure: If you have any questions or concerns, please […]
Forest Park Entrance Work to Begin Mid-May
Sent on behalf of Barnes-Jewish Hospital. Forest Park Forever and the City of St. Louis are enhancing access and beautifying the entrance to Forest Park at Kingshighway and Hospital Drive starting in mid-May. The project is expected to have minimal impact on traffic, but there may be occasional lane reductions and construction equipment on Hospital […]
5/15: South Newstead Lane Closure
Sent on behalf of Ameren. Ameren will proceed with underground work on the evening of Friday, May 15 (likely after 3 p.m.). During this time, one lane of traffic on South Newstead between Duncan and Clayton Avenues will be shut down, and traffic control will be in place. If you have any questions, please contact […]
April-August: Plaza Lobby Detour Changes
Sent on behalf of Barnes-Jewish Hospital. As renovations continue, areas reopen, and detours shift. Three new elevators to serve the main and street level lobbies opened in April. With the elevators, a new street-level lobby and atrium also opened, providing a street-level connection to the new Plaza West Tower. The corridor on the main level, […]
4/30-6/30: 4533 Clayton Avenue Building to Begin Construction
Construction will begin at the 4533 Clayton Avenue Building and run through the end of June 2026. The contractor will use the exterior stairway as the primary means of access, and a dumpster will be located on the west side of the building. There should be no disruptions to parking or daily operations. If you […]