Parking reminder for patient garages on the Washington University School of Medicine Campus

Sent on behalf of Barnes-Jewish Hospital. Barnes-Jewish Hospital and St. Louis Children’s Hospital are experiencing a large volume of faculty and staff, both WUSM and BJC, parking in the patient garages, including Parkview Garage, Laclede Garage, Plaza Garage, Euclid Garage and Children’s Hospital Visitor Garage. The activity involves paying the daily rates and various means […]

Leadership changes within the Operations & Facilities Management effective July 1, 2022

To support the Medical Campus growth, the Operations & Facilities Management Department has prepared a five-year organizational plan, including several leadership changes listed below, effective July 1, 2022. Jim Stueber, Senior Director, will transition to a strategic project role and step out of his direct leadership role in Facilities to support several critical initiatives for […]

Metro Bus terminal fence replacement

Workers will be replacing the Metro Garage Bus Terminal Fence starting Monday, June 27th. The fence runs along the southwest side of the Terminal east to Taylor Avenue. This is the north side of the BJCIH Service drive. The area around the sections of the fence that will be removed will be monitored to keep […]

MDAS construction in Group J starts June 28th

Sent on behalf of Barnes-Jewish Hospital. A Multi-carrier Distributed Antenna System (MDAS) will be installed over the next 18-24 months to provide cellular service for ATT, Sprint-T-Mobile, and Verizon connections throughout the Medical Center Campus. The construction will be completed in phases targeting specific building groups. What’s happening in your building?Construction in three buildings (BJCIH […]

MDAS construction in Group F starts June 27th

Sent on behalf of Barnes-Jewish Hospital. A Multi-carrier Distributed Antenna System (MDAS) will be installed over the next 18-24 months to provide cellular service for ATT, Sprint-T-Mobile, and Verizon connections throughout the Medical Center Campus. The construction will be completed in phases targeting specific building groups. What’s happening in your building?Construction in three buildings (Rand […]

Duncan Street closure Saturday, June 25th

A portion of Duncan Avenue, east of Newstead Avenue, will be closed on Saturday, June 25th, from 6 am to 3 pm. This closure will facilitate the hoisting of the electrical equipment into the New Research Building 11th floor penthouse. Please note, this closure is weather dependent and subject to change Please direct any questions […]

Large generator and transformer on 4444 south handicap parking lot starting June 22nd

A large generator and transformer will be installed on the 4444 South handicap lot to electrically support the 4444 Forest Park building while the building service feeders are transferred to the new Duncan substation switchgear. The entire South lot will be reserved for this work from June 22nd-July 31st. The handicap parking will be relocated […]

Concrete pour scheduled for TAB and TAB Extension

On Monday, June 20th at 8 am a concrete pour is scheduled for a disabled access ramp located between 600 and 620 S Taylor lots. There will be two disabled space out of use during this time period. There are five disabled spaces on the 600 South Taylor lot. We will open the two spaces […]

Revised Office Space Guidelines – June 2022

The Operations & Facilities Management Department (OFMD) planning team presented the revised Office Space Guidelines to the Executive Faculty this month. The guidelines received full support for ongoing programming use. In addition, the guidelines help to support efficient space planning and Hybrid and Remote work policies. These guidelines are available here and on the OFMD […]

MDAS Construction in Group J starts June 28th

Sent on behalf of Barnes-Jewish Hospital. A Multi-carrier Distributed Antenna System (MDAS) will be installed over the next 18-24 months to provide cellular service for ATT, Sprint-T-Mobile, and Verizon connections throughout the Medical Center Campus. The construction will be completed in phases targeting specific building groups. What’s happening in your building? Construction in three buildings […]