REVISED Specialized Research Facility East-Electric Service Interruption 11/7/2024

On Thursday, November 7, 7-11 am, facilities will conduct an emergency power test to determine if the 1800 Kw generator can support both SIRF and SIRF-East together, along with the chillers. There will be no loss of power to the SIRF building. SIRF-East will be the only building affected by this outage. SIRF-East utilities will […]

Mallinckrodt Institute Radiology-Electric Institute Radiology 11/3/2024

On Sunday, November 3rd 7-11 am, facilities will be conducting an electrical outage of the entire building. The purpose of this outage is to clean the (6) 5Kv. switches located in the basement of the MIR building. In order to safely perform the required work, the utility power must be turned off. The generator will […]

Biotechnology Center-Air Handling Unit 10/9/2024

On October 9th from 4 am to 7 am Air handling units 1 and 2 will be down for scheduled cleaning in the Biotechnology Center. In this time there will be limited to no air flow, heating, or cooling to the building.

REVISED-CSRB North Tower Addition-Humidifier Service Interruption 10/10/2024

On Thursday, October 10th 1:30-4:30 Pm maintenance work will be completed on the humidifier of the terminal equipment serving the NTA 452/462 suite. Although facilities do not expect any impact to the performance of the BSL3 lab as a precaution NO work shall take place in the 452/462 lab suite during the above-noted times.

Southwest Tower-Electric Service Interruption 10/14-17/2024

On Monday, October 14th, 17th, 5-7 am, Barnes facilities will be transferring normal power to emergency power to conduct maintenance on their switchgear. The affected floors will be the 6th, 7th, and 8th. There will be a blip during the transfer. There will be three outages: Monday, Tuesday Part B, and Thursday Part B.

McMillan Hospital-Air Handling Unit Service Interruption 10/26/2024

On Saturday, October 26, from 6 am to 2 pm, contractors will turn off air handlers serving floors, lower levels 2, and 9, and sections 3, 4, and 5 to make necessary repairs. During the above-noted dates and times, these areas will experience a loss of airflow and fluctuating temperatures.