On Tuesday, February 21st 5 am – 6 am the horn/strobe alarm notification devices will be tested in the 4th floor biohazard area. No work may occur in the 4th floor biohazard area during this testing.
Mallinckrodt Institute Radiology-Elevator Service Interruption 2/19/2023-3/19/2023
Elevator 103 will be out of service on Sunday, March 19, at 8 am for 4 hours to perform preventive maintenance. The elevator will be back in service at noon.
Mallinckrodt Institute Radiology-Elevator Service Interruption 3/5/2023
Elevator 102 will be out of service on Sunday, March 5, at 8 am for 4 hours to perform preventive maintenance. The elevator will be back on service at noon.
REVISED-Taylor Avenue Building-Elevator Service Interruption 3/13/2023-6/29/2023
Starting Monday, March 13, the TAB Service Elevator (#129) was taken out of service for modernization. The elevator will be out of service for about 20 weeks, returning to service Thursday, June 29th.
Renard Hospital-Hot Water System Service Interruption 3/3/2023
Facilities will be working on the heating hot water system on Friday, March 3rd 12 am – 7 am. The entire building may see cooler-than-normal temperatures.
CANCELED – Genome Data Center-Electric Service Interruption 3/1/2023
Facilities/Contractors will be troubleshooting the West Genome Data Center automatic transfer switch. On March 1st 8 am – 3 pm, there will be switching of breakers to simulate an outage to check the operation of the automatic transfer switch. During this testing we will be single-sourcing US-1 and US-2, we do not anticipate any interruption […]
Genome Data Center-Electric Service Interruption 2/28/2023
Facilities/Contractors will be troubleshooting the West Genome Data Center automatic transfer switch. On Tuesday, February 28th 8 am – 3 pm, there will be switching of breakers to simulate an outage to check the operation of the automatic transfer switch. During this testing we will be single-sourcing US-1 and US-2, we do not anticipate any […]
McDonnell Pediatric Research Building-Fire Alarm Service Interruption 2/23/2023
As part of the McDonnell Pediatric Research Building fire alarm project Facilities/Contractors will be programming and testing the fire alarm system. On Thursday, February 23rd 5-7 am you will hear messages and see strobes throughout the building, occupants do not need to leave the building during the testing. As a precautionary measure, no work may […]
825 S. Taylor Avenue, 4560 Clayton Avenue-Domestic Cold Water 2/25/2023
Facilities/Contractor will be installing a redundant backflow in the Central Institute for the Deaf School, this will also affect the Central Institute Research building. On Saturday, February 25th 4 am – 1 pm there will be no domestic water (Hot or Cold) in these buildings. This will affect sinks, water fountains, bathrooms, cage wash, and […]
McDonnell Pediatric Research Building-Fire Alarm Service Interruptions 2/23/2023
As part of the McDonnell Pediatric Research Building fire alarm project Facilities/Contractors will be programming and testing the fire alarm system. During the above time you will hear messages and see strobes throughout the building, occupants do not need to leave the building during the testing. As a precautionary measure, no work may occur in […]