Lane restriping on BJH Plaza today, January 4th

Sent on behalf of Barnes-Jewish Hospital.

Wet weather prevented contractors from restriping lanes of Barnes-Jewish Plaza near Kingshighway during evening hours last Wednesday and Thursday. The work is rescheduled for today, Tuesday, January 4th with the following impact:

• Between 8 and 11 a.m., restripe the furthest south lanes, which are behind the current construction barricade: no impact.
• At 11 a.m., remove barricades along the south and open the lanes.
• From noon to 3 p.m., barricade the middle lanes and restripe.
• Starting at 3 p.m., remove barricades from center and close the far north lanes to restripe.
• Complete all work by 5 p.m.
Flaggers will be on hand to direct traffic and reduce the congestion. Team members should avoid using Barnes-Jewish Plaza for the convenience of our patient and visitors.

Questions can be directed to Justin Breig, BJC project manager, at 314-323-2317.

Recommended travel routes:

The Tower Grove/Boyle Avenue ramps on Highway 40/Interstate 64, one exit east of Kingshighway, provide a convenient alternative to Kingshighway and Barnes-Jewish Plaza for team members to access parking, including the Plaza Garage. These exits were constructed to ease traffic for patients and visitors.