Facilities Operations Update

WUSM Infrastructure and Garage Update-conduit construction Phase 1

Please see the additional traffic control drawings for our continued conduit work south of the MetroLink tracks and Newstead, south of Clayton. (Newstead Intersection PH1, Newstead Intersection PH2, Newstead Intersection PH3, N Clayton Ave PH2 and N Clayton Ave PH3).

Currently the conduit work south of the MetroLink tracks is expected to continue until March 4, 2022. The conduit work will then continue north of the MetroLink tracks.
Cable work is anticipated to begin south of the tracks after March 4, 2022.

If you have any questions please contact Mitch Snyder, Senior Project Manager.