New Research Building link logistics plan

This week, contractors will be pouring concrete on Level 5 of the SLCH Employee Garage.

  • Work will start around 9am to avoid the morning rush hours when the garage is most busy and complete prior to the evening rush.
  • The concrete truck would be staged in the lane drop in front of the daycare. The truck would be able to move if there were any reason that required it to do so.
    • Concrete would be transported by buggy through the drive lanes up to level 5 in the direction of traffic flow. At no times would vehicular traffic be stopped or blocked during the process.
  • We will provide a flagger for precaution.

Please contact Mitch Snyder with any questions.