The access drive between the West Building and BJCIH leading to the loading docks, and the loading docks will be closed on three upcoming Saturdays to place a crane for roof top work on the Renard building. The upcoming dates are:
Saturday #1: Removal of roof top equipment and ductwork outside of the Air Handler
Date: 3/11/23
Duration: 6am – 4pm
Saturday #2: Removal of existing Air Handler equipment and ductwork
Date: 4/01/23
Duration: 5am – 6pm
Saturday #3: Setting new AHU Equipment at the roof
Date: 4/29/23
Duration: 5am – 6pm
This work is weather permitting and will be rescheduled in case of inclement weather.
For any questions, please contact Paul Duell, Senior Project Manager.