The access drive between the West Building and BJCIH leading to the loading docks, and the loading docks will be closed on three upcoming Saturdays to place a crane for roof top work on the Renard building. The upcoming dates are:

Saturday #1: Removal of roof top equipment and ductwork outside of the Air Handler

Date: 3/11/23
Duration: 6am – 4pm

Saturday #2: Removal of existing Air Handler equipment and ductwork

Date: 4/01/23
Duration: 5am – 6pm

Saturday #3: Setting new AHU Equipment at the roof
Date: 4/29/23
Duration: 5am – 6pm

This work is weather permitting and will be rescheduled in case of inclement weather.

For any questions, please contact Paul Duell, Senior Project Manager.