Due to predicted weather conditions (high winds) on Saturday, April 1, 2023, we are shifting our planned crane lift in the Renard Dock area to Sunday, April 2, 2023.
The access drive between the West Building and BJCIH leading to the loading docks, and the loading docks will be closed on three upcoming Saturdays to place a crane for roof top work on the Renard building. The upcoming dates are:
Saturday #2: Removal of existing Air Handler equipment and ductwork
Date: 4/02/23
Duration: 5am – 6pm
Saturday #3: Setting new AHU Equipment at the roof
Date: 4/29/23
Duration: 5am – 6pm
This work is weather permitting and will be rescheduled in case of inclement weather.
For any questions, please contact Paul Duell, Senior Project Manager.