Sent on behalf of Barnes-Jewish Hospital.
Please be aware that beginning the week of April 22nd, Sachs Electric (ArchKey) will be working on the Medical Campus to conduct a manhole audit on Forest Park Avenue.
Weather permitting, the planned duration of this work is from May 6th to May 17th. All work will be done during the day shift, starting at 9 am and ending at 3 pm daily. There are NO anticipated street closures, but intermittent lane obstructions and traffic shifts will occur.
Adhering to Federal, State, and Local transportation regulations, the contractor will provide traffic and safety control during all work times, including flagmen, cones, plating (where appropriate), and warning signs.
For any questions, please contact Greg Klaric at 225.803.2142.