Facilities Operations Update

East Building roof replacement update

Crane picks are scheduled for Wednesday, October 16th and Thursday, October 17th.

To avoid vehicular and pedestrian traffic on Scott Avenue, all crane picks will occur from the service alley on the north elevation of the building. The last crane pick is scheduled for 8 hours on November 4th.

Workers began the replacement of the East Building’s roof on September 9th. The demolition phase has been completed. The roof replacement is scheduled for October 7th – November 4th, during the hours of 7 am – 5 pm.
Please share this information with your vendors to assist with planning their pickups and deliveries for the scheduled dates. Please remember that all dates are subject to change due to inclement weather.

If you have any questions, please contact Antwoine Feaman, Engineering Project Manager.