Facilities Operations Update

McMillan survey next week

The Operations & Facilities Management Department and architect and engineer representatives will survey the McMillan Building from January 27 to January 31.

The survey participants will walk the 10th through 13th floors and the core areas from the lower level through the 9th floor with WashU Med representatives. They will be mindful of occupants and expect minimal impacts on daily activities.

They will complete 3D scans of the building and take some photographs while reviewing conditions. They will blur all people and any sensitive materials captured. The architects and engineers will use the images and scans for building renewal.

If you have any questions, please contact Bob Korte, Team Lead Senior Project Manager.