Clinical Sciences Research Building North Tower Addition (CSRB-NTA) ninth-floor link elevator lobbies upgrade February 3-May 30

United Construction will upgrade the elevator lobbies in the CSRB-NTA from February 3rd through May 30th. The scope includes the area from the door to the CSRB to the expansion joints at the McDonnell Pediatric Research Building. Traffic will be rerouted during the construction for each floor and will take approximately 2 weeks per floor. Here is a link to the floor plan schedule.
• 4FL Feb. 3 – 14th
• 7FL Feb 17 – 28th
• 10FL Mar 3 – 14th
• 2FL Mar 17 – 28th – (night work)
• 3FL Mar 31-April 4th – (night work)
• 8FL April 7 – April 18 – (night work)
• 6FL April 21- May 2
• 9FL May 5 – 16th – (night work)
• 5FL May 19 – 30th

If you have any questions, please contact Antwoine Feaman, Engineering Project Manager.