Due to scheduled construction work, temporary access will be restricted to the Newstead Garage’s west entrance only (Newstead entrance).
The north entrance on Duncan Avenue will remain open and unaffected during this time. This work will take place in three phases over the next two weeks:
Phase 1: Demo – NO ACCESS (April 1 – April 2)
Phase 2: Structural & Fireproofing – ONE LANE CLOSED (Entrance & Exit) (April 3 – April 8)
Phase 3: Patch Back EIFS – NO ACCESS (April 9 – April 11)
Please plan accordingly and use alternate access points as needed during these times. Signage and cones will be placed at the top and bottom of the ramp to help direct traffic.
We appreciate your patience and cooperation as we work to complete these improvements.
If you have any questions, please contact Adam Jones, Project Manager – Design & Construction.