Facilities Operations Update

March 31-May 20: East McDonnell Repairs and Cleaning of Facade

From March 31st to May 20th, Western Specialty Contractors will repair the limestone bands and clean the east façade of East McDonnell. The work will be divided into six phases.

In the first five phases, which will commence on the north side of East McDonnell, Western will utilize a swing stage to carry out their work during regular working hours. For the sixth phase, they will employ a combination of a swing stage and a lift; this work will be done during the nighttime hours of 9 pm to 5 am. See the schedule detailing the phases of their mobilization, including alternate routes for sidewalk closures.

*This schedule does not account for weather delays and is subject to change.

If you have any questions, please contact James Wade, Contracted Services/Project Coordinator I.