Bernhard Engineering/ENFRA will begin investigating the entire Barnard exhaust fan #3 system throughout the building. This will consist of an ENFRA/Bernhard Engineer walking around the whole building and following the ductwork through the ceilings to create an as-built of the system. They will remove ceiling tiles and look above the ceilings as needed throughout the building.
This will take 2-3 months to complete. It is expected to be completed around the end of July or August.
If you have any questions, please contact Rick Myers, Senior Project Manager.