Sent on behalf of Barnes-Jewish Hospital.
The east/west corridor along the construction project will close on the following dates. The weekend closures are expected to minimize disruptions to patients, families, and team members, while the weekday closure is less extensive.
Detours will be in place, with directional signage. The construction teams aim to reopen and make the corridor accessible as soon as possible after each closure.
Please help our families by becoming familiar with the maps and directing them as needed.
Closure #1, Friday, Aug. 29, at 5 p.m. through Monday, Sept. 1, midday
- During this corridor closure, the Dialysis/Pheresis area and Suite 2A (Surgery Clinic, General Plastics and Urology) will be accessible only through the east hospital entrance from the link. See Detour Map 1.
- When the work concludes, the corridor will fully reopen. Closure #2: Friday, Sept. 5, at 5 p.m. through Sunday, Sept. 7, midday
- During this corridor closure, the Dialysis/Pheresis area and Suite 2A (Surgery Clinic, General Plastics and Urology) will be accessible only through the east hospital entrance from the link. The detour is the same as closure #1. See Detour Map 1.
- When the work concludes, the corridor will fully reopen – see closure #3.
Closure #3 – Monday, Sept. 8 to Sunday, Sept. 14 by 5 p.m.
- This closure is less extensive.
- Dialysis/pheresis and Suite 2A (Surgery Clinic, General Plastics and Urology) will be accessible as depicted in Detour Map 2.
- Work is anticipated to conclude on Friday; however, the weekend days are a contingency.
If you have any questions, please contact Peter Moen, BJC Senior Project Manager, at Peter.Moen@bjc.org or 314-766-0865.