Facilities Operations Update

September 23-29: Street Work by the Gary C. Werths Building at Siteman Cancer Center

Sent on behalf of Spire.

Spire will be reworking underground gas piping that serves the Gary C Werths Building at Siteman Cancer Center. Most of the work will be in the exit lane for the BJC North Dock. On September 26, one of the two entrance lanes for the Werths Building will be blocked for a Spire natural gas trailer to support the building while the work is being done on the gas main for the building.

Spire Working Areas
• Thursday, September 25 – Pre-work & slab removal – BJC dock exit lane partial restriction
• Friday, September 26, work for piping replacement – BJC dock exit lane partial restriction & one entrance lane at the 4500 block for a temporary gas cart.
• Monday, September 29, slab replacement – BJC dock exit lane partial restriction