October 14-16: McDonnell Medical Sciences Building Dock Repairs

The cleaning and restriping of the McDonnell Medical Sciences Building dock is scheduled from October 14 to 16. Please see the scope of work document, which outlines the affected areas.

  • October 14: Repair the concrete stairs by the Olin entrance and the concrete ramp on the West side of the dock, and start the prep work for painting the safety yellow
  • October 15: Finish concrete repairs and painting of all safety yellow columns, bollards, and rails.
  • October 16: (Evening shift starting at 5 p.m.): Restripe and letter the dock bays.
    No closure will be required for this work.