1/12-13: Changes to DAS System at Mid Campus Center

BJC’s Technology purpose is to deliver resilient and secure technology that drives innovation in alignment with BJC Heath System priorities.  

  • On Monday, January 12th and 13th, 2026, from 6:30 am to 3:30 pm, the Voice team will perform Distributed Antennae System (DAS) changes at the Mid Campus Center.
  • AOnAir will be onsite working with ArchKey to test the existing DAS cabling infrastructure.
    • CHG0382282 – MCC/DAS/OnAir Test Existing Cabling for the DAS Upgrade – Jan 12
    • CHG0382283: MCC/DAS/OnAir Test Existing Cabling for the DAS Upgrade – Jan 13

This change readies the infrastructure for the DAS equipment upgrade. 

  • Anticipated Impact: High – During testing, there will be about a 2-hour period of cellular service degradation. Users will still have cellular coverage from the outside cell towers in the area. No impact to the network, wireless network, Epic, Vocera or clinical operations.
  • 1/12 Impact time and Location:
    • 6:30 am to 8:30 am, Lower Level & 1st Floor
    • 8:30 am to 10:30 am, 2nd Floor
    • 10:30 am to 12:30 pm, 3rd Floor & 4th Floor
    • 1:30 pm to 3:30 pm, 5th Floor & 6th Floor
  • 1/13 Impact time and Location:
    • 6:30 am to 8:30 am, 7th Floor & 8th Floor
    • 8:30 am to 10:30 am, 9th Floor & 10th Floor
    • 10:30 am to 12:30 pm, 11th Floor
    • 1:30 pm to 3:30 pm, 12th Floor