4/20: Medical Campus Fiber Pulling on Clayton Avenue

Sent on behalf of Barnes-Jewish Hospital.

Beginning April 20, Archkey will be working on the Medical Campus to conduct fiber-pulling activities in the 4200 and 4300 blocks of Clayton Avenue.

Weather permitting, the planned duration of this work is from April 20 to May 1.

All work will be done during the day shift, beginning daily at 8 a.m. and ending at 3 p.m. each day. There are NO anticipated street closures, but an intermittent lane closure and traffic shifts will occur.

Adhering to Federal, State, and Local transportation regulations, the contractor will provide traffic and safety controls, including flagmen, cones, plating (where appropriate), and warning signs, during all work times.

Please notify your staff of this disruption and share this information with anyone you deem appropriate.

If you have any questions, please contact Greg Klaric at 225-803-2142.

Impacted Area: