Sent on behalf of Barnes-Jewish Hospital.
Contractors will begin building walls to cordon off the vacated street-level lobby of St. Louis Children’s Hospital (SLCH) on Thursday, July 23, in preparation for construction of a new canopy at the emergency department (ED) drop-off area. The canopy construction is the first of several phases to improve the Emergency Department entrance, triage and lobby.
- Starting Tuesday, July 21, a film will be applied to the lobby windows to block the view of the construction materials, which will be staged and stored in the lobby for the project.
- Access to the emergency department on the street level will be maintained, as well as egress as shown in green on the graphic.
- Details of the canopy construction will be shared by mid-August, with construction scheduled to begin in late August and continue through January.
- The main entry phases of the project will begin in September and continue through February. More information will be shared as the time approaches.
If you have any questions, please contact Peter Moen, BJC senior project manager, at Peter.Moen@bjc.org or 314-766-0865.