Facilities Operations Update

Overnight utility work in Barnes-Jewish Plaza April 10-12

Sent on behalf of Barnes-Jewish Hospital

From April 10-12, starting after the evening rush hour, Campus Renewal Project contractors will work in the westbound lanes of Barnes-Jewish Plaza, west of the pedestrian bridge, with full and partial closures planned as outlined below. The work is expected to begin around 7 pm and conclude by 5 am each morning.

• April 10 and 11 – On the first two evenings and overnight, both westbound lanes of Barnes-Jewish Plaza will be closed. Detour signs will direct drivers exiting the garage to Euclid Ave., Clayton Ave., Hospital Drive to Kingshighway.

• April 12 – On the third evening, one westbound lane will be open, with no detour.

• Eastbound traffic will not be affected.
Work will conclude all mornings before morning rush hour. Traffic control personnel will help to direct motorists safely around the work.

For any questions, please contact Justin Breig, BJC project manager, at 314-323-2317.