Facilities Operations Update

Street Work Notification – Clayton Avenue

Sent on behalf of Barnes-Jewish Hospital.

Please be aware that beginning the week of June 3rd, Sachs Electric (ArchKey) will be working on the Medical Campus to conduct manhole audit activities on Clayton Ave. Please see the location for more information. The entrance and exit to the Clayton Avenue Building parking lot will not be blocked or impede shuttle traffic.

Weather permitting, the planned duration of this work is from Monday, June 3rd through close of business, Friday, June 14th.
All work will be done during the day shift, beginning daily at 9:00 am and ending at 3:00 each day. There are NO anticipated street closures involved, but an intermittent lane obstruction and traffic shifts will occur.

Adhering to Federal, State, and Local transportation regulations, the contractor will provide traffic and safety control to include flagmen, cones, plating (where appropriate), and warning signs during all work times.

For any questions, please contact Greg Klaric at 225.803.2142.