Facilities will be working with contractors on the air handlers that serve the 4th floor. Each unit will be shut down one at a time until the work is complete during the times and dates noted above. Temperature fluctuations may be noticed during this time.
Author: Madison Denton
6/2-16: Limited Service Interruption – McDonnell Pediatric Research Building, Other
From 6/2-12, the 7230 A/BSL3 suite will be unavailable for research to accommodate a decontamination and subsequent maintenance and recommissioning of the suite. NO work may occur in the 7230 A/BSL3 suite during this outage.
6/20: Planned Service Interruption – Gary C. Werths Building at Siteman Cancer Center, Electric
On 6/20, from 12 pm to 4 pm, facilities will be conducting a load bank test of the generator at Gary C. Werths at Siteman Cancer Center. During the test, there will be no power loss, no power blips, and no power sags. The generator will run for 4 hours to complete the test.
6/20: Planned Service Interruption: South Building, Exhaust Fan
On 6/20, from 6 am to 3 pm, Exhaust Fan 8C will be shut down to facilitate the replacement of the variable frequency drive (VFD). During this outage, the following fume hoods will not have airflow and should not be used. Fume hoods, 1902,1905, 1906, 1911B, and 1914 on the first (1st) floor. Fume hoods […]
6/18-19: Planned Service Interruption – BJC Institute of Health, Air Handling Unit, Exhaust Fan
During the dates and times noted below, facilities technicians will be performing preventative maintenance on the HVAC systems serving the 11th-floor ABL suite and the B120 suite located in the basement. During these maintenance periods, no work shall be conducted in either lab suite. Thursday, June 18th – 5:00 AM to 7:00 AMFriday, June 19th […]
6/13: Limited Service Interruption – South Building, Air Handling Unit
On 6/13, from 6 am to 3 pm, Air Handling Unit #3 serving the 3rd, 4th, and 5th floors will be shut down to replace the supply air variable frequency drive (VFD). During this outage, there will be no airflow, heating, or cooling capabilities. Thank you for your patience.
6/6: East McDonnell Roof Replacement
Missouri Builders will be closing off the sidewalk between the East McDonnell Building and the Couch Building on Saturday, 6/6/26, to use their crane to complete the South roof on the East McDonnell Building. Additionally, the diagram shows 5 parking spots on Scott Ave that will need to be blocked off on Monday, June 8th, […]
6/8: Composting Pilot Program at the Jeffrey T. Fort Neuroscience Research Building (Fort Labs) Kaldi’s Location
Composting is being piloted at the Kaldi’s location inside the Fort Labs Building starting June 8, and volunteers are needed to make the program successful! Volunteers will educate Kaldi’s customers about waste sorting during lunchtime to reduce contamination, and no experience is required. Learn more and sign up here.
6/1: Crane Operation to Remove Debris from East McDonnell Building
On June 1, a portion of the sidewalk between the Couch Building and East McDonnell will be temporarily closed. Missouri Builders will use a crane to remove materials and debris from and off the south roof of the East McDonnell Building. The diagram below shows the closure area and alternative pedestrian routes to use during […]
6/6: Crane Operation on South Side of East Imaging Building
On June 6, from 6 a.m. to 9 a.m., Taylor Roofing will be operating a crane on the south side of the East Imaging Building as part of Project #230019 – East Imaging Roof Replacement. Below is a diagram showing the area closure required for crane operations, and the location of an additional truck and […]