On Wednesday, February 12th, from 6 am to 2 pm, exhaust fan 18 will be shut down to facilitate the construction of the 9th-floor renovation project and ensure the safety of the electrical technicians changing the electrical feeds and control wiring. The areas affected are the 9th and 7th-floor labs and equipment that use exhaust […]
Author: Michelle
East Building-Elevator Service Interruption 2/17/2025
On Monday, February 17th, 2-6 am, as part of the modernization project, both elevators (#47 & #48) will be removed from service to allow contractors to perform work in the elevator shaft safely. Elevator #48 will be returned to service by 6 am.
CSRB North Tower Addition-Domestic Cold Water Service Interruption 2/12/2025
On Wednesday, February 12th 4-6 am, the domestic cold water to the 4th floor will be shut off during the outage to accommodate tying in a new water cooler in the 4th floor elevator lobby area. No domestic cold water will be available to restrooms (faucets, urinals, toilets), showers, and service sinks on the 4th […]
East Building-Elevator Service Interruption 2/10/2025
Elevator #48 will be removed from service for repairs from 5 am to 6 am on Monday, February 10th. As soon as the repair is complete it will be returned to service.
McDonnell Medical Sciences Building-Domestic Cold Water Service Interruption 2/6/2025
On Thursday, February 6th 1-6 am there will be no domestic cold or hot water during this time. This outage is to facilitate the 9th floor renovation project in order to tie in the domestic water systems. This will effect all sinks, toilets, autoclaves, Ice Machines, vacuum systems and any other device that utilizes hot […]
McDonnell Pediatric Research Building-CO2 Service Interruption 2/13/2025
On Thursday, February 13th, from 5 to 9 am, CO2 serving the 9th floor will be offline so the tie-in of the newly installed regulators on the floor can be performed. During this time, please ensure that any incubators or experiments utilizing CO2 have the appropriate and necessary means for this work to be completed.
Taylor Avenue Building-Domestic Cold Water Service Interruption 2/5/2025
On Wednesday, February 5th, 6 am – 2:30 pm. Domestic water service, including cold and hot water, will be shut down temporarily to facilitate water tie-in for the Childcare project. During this time, the entire facility will not have water in the building from the indicated times. When water is restored on the same day, […]
McKinley Avenue closure for crane pick – February 15-16
McKinley Avenue will be closed February 15-16 between the 4522 McKinley building and the 718 S. Euclid parking lot entrance. This closure will allow a crane to place a new air handler on the McDonnell Science Building. A flagger will direct traffic at the corner of McKinley and S. Taylor. There will be barriers between […]
Wohl Clinic stairwell painting all floors February 10-March 21
Wohl Clinic stairwell painting will occur from February 10th to March 21st , between 6 am and 2 pm. The project involves painting and repairs in the west stairwell of Wohl Clinic and will take place in 3 phases. Throughout each phase, multiple floors will be closed, and wayfinding signage will be posted to direct […]
Thursday, February 13th – Bon Appetit’s regional dietician visits campus
Stop by the McDonnell Pediatric Research Building lobby on Thursday, February 13th, 11 am-1 pm, to chat with Leslie Mathiasmeier, Bon Appetit’s regional dietician, who works with the WashU Medicine Bon Appetit team to create menu offerings for their on-campus cafes and catering. Leslie’s knowledge and commitment to being a champion for better health & […]