East Building roof replacement update

Crane picks are scheduled for Wednesday, October 16th and Thursday, October 17th. To avoid vehicular and pedestrian traffic on Scott Avenue, all crane picks will occur from the service alley on the north elevation of the building. The last crane pick is scheduled for 8 hours on November 4th. Workers began the replacement of the […]

East Building-Domestic Hot Water 10/21/2024

On Monday, October 21 from 4 am to 8 am the domestic hot and cold water will be off to tie in lines for the construction in the east area of the East building. During this time, there will be limited to no domestic hot and cold water to restrooms, sinks, and anything else requiring […]

Taylor Avenue Building-Domestic Hot Water Service Interruption 10/21/2024

On Monday, October 21st from 4 am to 8 am the domestic hot and cold water will be off to tie in lines for the construction to the east area of the Taylor Avenue building. During this time, there will be limited to no domestic hot and cold water to restrooms, sinks, and anything else […]

REVISED-Wohl Clinic-Elevator Service Interruption 11/4-12/2024

Access to the Lower Level of Wohl Clinic from elevators #13, 14, 15, 16 & 17 will be disabled between 4 pm and 6 am, starting Monday, November 4. This restriction will occur nightly to allow contractors to replace flooring in the elevator lobby at the lower level, through Tuesday, November 12th. Wohl Hospital elevators […]

Wohl Hospital-Elevator Service Interruption October 30 – November 1

On Wednesday, October 30, starting at 6 am, elevators #18 and 19 will be taken out of service to allow contractors to replace flooring in the lower-level elevator lobby. Please use elevator #20, located at the south end of the building, during this time. The elevators will be returned to service on Friday, November 1, […]