North Building roof replacement

From November 20th to December 18th, contractors will work Monday to Friday from 6 am to 2:30 pm. During this time, the south sidewalk heading west beyond Olin Residence Hall, the east Farrell Learning & Teaching Center (FLTC) entrance, and the FLTC ADA entrance will be closed due to a crane operating on the east […]

WUSM Ambulatory Cancer Center (ACC) public realm work – Taylor asphalt

In conjunction with the public realm work, we are ready to perform the mill and overlay of Taylor Avenue from Duncan and Taylor to Forest Park and Taylor. We plan to do this on Thursday, November 2nd, 7 am – 9 pm and Friday, November 3rd, 7 am – 9 pm. Please see the plan […]

CSRB 2nd floor link renovations

On October 10th, work started on the 2nd-floor link renovations. This includes painting, new carpet, and replacing a drinking fountain. This work will be done at night and scheduled to be completed by December 29th. For any questions, please contact Jean Thole, Interior Designer II.

Farmstead Café – modified hours Wednesday, November 1st

On Wednesday, November 1st, the Farmstead Café will be closing early at 2:00 pm. They will resume normal hours of operation on Thursday, November 2nd (7:00 am-4:00 pm). For any questions, please contact Lauren Hurt, Program Manager – Auxiliaries.

West side of Maternity tuckpointing starts October 30th

On Monday, October 30th, tuckpointing on the west side of Maternity will begin. Workers will begin rigging a swing stage for the first drop of the project. The swing stage rigging will be completed during normal dayshift hours. The project will be completed between the hours of 6:00 pm – 8:00 am, to avoid noise […]

Clinical Sciences Research Building North Tower Addition (CSRB-NTA) roof replacement – crane in McDonnell Pediatric Research Building (MPRB) garden October 30th – November 17th

On Monday, October 30th, the CSRB-NTA roof replacement project will begin. Workers will set a crane in the MPRB garden for the project, October 30th – November 17th. During this time, the walking path leading to the north entrance, the north garden seating area, and the north entrance of MPRB will be closed. The two […]

Main level corridor to West Pavilion elevators closing October 27th

Sent on behalf of Barnes-Jewish Hospital. On October 27th, the main level corridor to the West Pavilion elevators will close as contractors renovate the area. This will remain closed through the end of the year. Impacts include the following:• The West Pavilion elevators will not be accessible on the main level, nor will they stop […]

Drive lane repair at Newstead entry to SLCH Staff Garage

Sent on behalf of Barnes-Jewish Hospital. Washington University School of Medicine contractors will replace broken concrete slabs at the Newstead entry to the SLCH Staff Garage. For traffic to remain as-is, work will be performed in two phases, which began the week of October 16th. Each phase is expected to take three to four days […]

WUSM Ambulatory Cancer Center (ACC) public realm work – Taylor asphalt

In conjunction with the public realm work, we are ready to perform the mill and overlay of Taylor Avenue from Duncan and Taylor to Forest Park and Taylor. We plan to do this on Thursday, November 2nd, 7 am – 9 pm and Friday, November 3rd, 7 am – 9 pm. Please see the plan […]

Watch highlights of the pedestrian bridge lift

Sent on behalf of Barnes-Jewish Hospital. Weeks of planning went into the September 23rd pedestrian bridge lift over Barnes-Jewish Plaza, which took less than 30 minutes to complete. Watch the highlights here as the largest crane of its kind in the St. Louis area lifted the 182,000-pound steel structure. Bridge fun facts Visit the Campus […]